Vizsla Silver Delays Panuco Project Production to 2028
Vizsla Silver delayed first production at its Panuco project in Mexico to 2028 following the abduction and killing of 10 workers in Sinaloa.
Vizsla Silver delayed the target for first production at its Panuco project in Mexico by one year, now aiming for the second half of 2028. The shift follows the abduction and killing of 10 workers in Sinaloa on January 23, an event that forced the company to suspend all site work.
In response to the tragedy, the company committed US$5 million to a community foundation in Sinaloa and pledged a share of future profits. While engineering is approximately 50% complete and most processing equipment has been ordered, the company still requires federal environmental and land-use approvals before construction can begin.
Mexican federal authorities and the defense ministry reported several arrests linked to the killings. The company is currently coordinating a phased return to the site with security advisers and government officials.