Google Signs Deal for Superhot Geothermal Power in Oregon
Google signed a power purchase agreement with Quaise Energy to acquire 50 megawatts of superhot geothermal electricity for its Oregon data centers starting as early as 2030.
Google signed a power purchase agreement with Quaise Energy to acquire 50 megawatts of superhot geothermal electricity from Project Obsidian in Central Oregon. The carbon-free energy is intended to support Google's AI data center operations in The Dalles and surrounding communities, with deliveries expected to begin as early as 2030.
Project Obsidian, located near the Newberry Volcano, will be developed in two phases. The initial phase will use conventional drilling, while the second phase will deploy experimental millimeter-wave drilling technology developed at MIT. This technology uses a gyrotron to vaporize hard rock at depths of 3 miles, reaching temperatures between 315°C and 365°C to generate up to 10 times more power per well than traditional systems. The project will require a 10-mile transmission line to connect to a substation in La Pine.
The deal follows a $180 million Series B financing round for Quaise Energy in August 2026, which included a $35 million investment from Nabors Industries. While The Wall Street Journal values the agreement at over $500 million, Quaise estimates the project cost at roughly $350 million. The development is expected to create 200 to 400 construction jobs and over 50 permanent high-skilled positions.
Local officials in Deschutes County have called for greater transparency and community engagement regarding energy availability for residents. The project is part of a broader effort by technology companies to secure clean, off-grid electricity to meet the high power demands of AI.