ThinkPatternGet the app
Story
BUSINESS · NOV 20, 2026

NextDC Halts Residential Data Center Builds After Share Crash

NextDC will stop pursuing data center developments near residential properties following community protests in Melbourne and a significant drop in share price.

Data center operator NextDC announced it will no longer pursue new developments near residential properties following intense community backlash over its M3 site expansion in West Footscray, Melbourne. The controversy escalated when power provider Jemena paused the construction of 22-meter power poles due to local protests, contributing to a 40% drop in the company's share price. This decline allowed rival Goodman Group to acquire a nearly 10% stake in the company.

During its annual general meeting on Friday, CEO Craig Scroggie took responsibility for failures in planning and community support, noting that expectations have shifted in the age of artificial intelligence. Scroggie forewent bonuses up to $7.5 million, while shareholders issued a second strike against executive pay. To repair local relations, the company is establishing a community consultative committee and formal contact channels for residents.

Financial impacts have been severe, with NextDC cutting capital expenditure by $750 million and shaving $140 million off its 2026/27 guidance in October. While the company slightly raised its 2026/27 underlying earnings guidance to between $260 million and $275 million, this outlook excludes the affected M3 contracts. Shares fell an additional five percent to $9.21 following the meeting.


Reported across 32 outlets
Actors
NextDCCraig ScroggieJemenaGoodman Group